Refurbishment of school toilets

Over the last four years we have completed refurbishments to numerous school toilets during the school summer breaks.

The latest project was eight toilet blocks between Eaglesham Primary School and Carolside Primary School in July/August 2019 with a budget of £350,000.

Works included all down-takings, installation of new WCs, urinals, wash hand basins, cubicles with full height partitions, light fittings, extract fans, suspended ceilings, doors, Whiterock walls and mirrors.

With a six week turnaround time our team had to work hard to ensure the refurb was completed in time for the schools returning for the new term.

Once again, the project was handed over within the timescale and budget and the staff and children were delighted with their new, modern facilities.